DQuadrant - GovTool Maintenance

  • Supplier: Dquadrant

  • Contract Name: GovTool Maintenance - Integrated Testing

  • Contract Date: 1st April 2025 - 30th June 2025

Contract Details

Milestone Name
Milestone Completion Date
Milestone Description
Milestone Amount
Milestone Status
Milestone Acceptance Form

Milestone 1 - Maintainers role

Deliver monthly by 30th June 2025

The Supplier shall provide and carry out the following:

  • Develop and improve DApp level tests for GovTool on Preview, PreProd and Mainnet

  • Support governance actions loader

Acceptance Criteria:

  • Develop and execute DApp level tests for GovTool

  • Potential additional services or tests are identified and documented

  • Tests should include, but aren't limited to, the following:

    • Integration testing

    • System (end to end) testing

    • Performance testing

      • Load testing

      • Stress testing

      • Scalability testing

    • Security testing

      • Penetration testing

    • Regression testing

    • Smoke testing

    • Sanity testing

    • API testing

  • Testing should have several forms

    • Automation testing ○ Manual testing ○ Continuous Testing: Integrating testing into the CI/CD pipeline

€9,500

Not Started

Milestone 2 - Maintainers role

Deliver monthly by 30th June 2025

Same as above

€9,500

Not Started

Milestone 3 - Maintainers role

Deliver monthly by 30th June 2025

Same as above

€9,500

Not Started

Last updated